UST REMEDIATION/CLOSURE
Project Highlights:
​
-
Commercial property in South Buffalo, NY
-
Pending sale was complicated and jeopardized by open NYSDEC Spill
-
Phase II Investigation identified elevated VOCs and SVOCs above CP-51 SCOs
-
Waste characterization performed during investigation to obtain disposal pre-approval expedited the remediation
-
2 x 2,000 gallon gasoline USTs removed
-
1 x 2,000 gallon fuel oil UST removed
-
Removal of approximately 200 tons of petroleum-impacted soil
-
Clean crusher run (No. 2) backfill compacted to match existing grade
-
NYSDEC Spill closure achieved and property sale completed successfully

Phase II Investigation
Drilling

Excavation mark-out

Backfill compaction